SAT report
After the Site Acceptance Test (SAT) a report is made and sent to the customer and other parties involved. The report contains at least the following information. When required, a more detailed report is made.
- Location
- Address
- Date
- Teleport Device hash-ID
- Asset(s)
- Asset identifier
- Read all registers: Successful / Not successful
- Write curtailment setpoint: Successful / Not successful
- Curtailment test for each asset
- Market tests:
- FCR
- aFRR
- CBC
- Active dynamic control and/or static feed in limit: Yes/No
- Primary device communication
- Secondary device communication
- Signal strength
- Contact during outage (to)
- Contact during outage (cc)
- Data forwarding destinations
- API control
- Teleport functionalities
- Nominal power of each asset
- Remarks